Genesis Energy Limited lodged an application in April 2025 to continue operating and maintaining the Tekapo power scheme, which includes Tekapo A and B power stations and substations, and the canal system.
“Genesis Energy initially applied for a standard RMA resource consent in July 2023. A year into the process, Genesis indicated that further delays were likely due to the council hearing process and the potential for appeals. Genesis then applied for fast-track on April 2025, with the process taking just 80 days once a panel was appointed,” Mr Bishop says.
The decision | Tekapo Power Scheme – Applications for Replacement Resource Consents
Read more here: Fast-track renewable energy project green-lit | Beehive.govt.nz