Approvals granted 18 December 2025

The expert panel for the Kings Quarry Expansion – Stages 2 and 3 project granted approvals for the application, subject to conditions.

The decision

Project summary

Expand existing quarrying activities to enable the extraction and processing of up to approximately 500,000 tonnes per annum for up to 100 years (up to 60 years for Stage 2 and up to 40 years for Stage 3).

Project location

60 hectares (of 152-hectare total site) at 306 Pebble Brook Road, Wainui, Auckland.

Project listing application

Kings Quarry Expansion – Stages 2 and 3 application – Ministry for the Environment website

Completeness decision

The substantive application by Kings Quarry Limited was deemed complete on 4 June 2025. The application complies with the requirements of section 46 (2) of the Fast-track Approvals Act 2024. The application was lodged on 13 May 2025.

Decision on compliance with section 46 - Kings Quarry substantive application (PDF, 70KB)

Competing applications decision

The substantive application by Kings Quarry Limited was deemed to not have any competing applications or existing resource consents on 18 June 2025. This decision is required under section 47 of the Fast-track Approvals Act 2024.

Record of decision on competing applications − Kings Quarry substantive application (PDF, 67KB)

The application has now been referred to the panel convener for determination by a panel.

 Decision of appointment of panel and timing of panel decisions

On 30 July 2025, the panel convener issued a Minute. This covers:

  • the appointment of the expert panel

  • the timeframe for panel decisions for the Kings Quarry Expansion – Stages 2 and 3 project under clause 2 of section 79 of the Act.

The minute can be viewed on the Correspondence page for the Kings Quarry Expansion – Stages 2 and 3 project.

Correspondence

  • Substantive application

    The application documents for the Kings Quarry project.
    Substantive application
  • Correspondence

    Minutes, directions and other correspondence to and from the panel convener and expert panel for the Kings Quarry Expansion Stages 2 and 3 project.
    Correspondence
  • Reports and advice

    Reports, advice and further information sought in relation to the Kings Quarry Expansion – Stages 2 and 3 project.
    Reports and advice
  • Conferences, workshops and hearings

    Watch and learn more about conferences, workshops and hearings in relation to the Kings Quarry Expansion – Stages 2 and 3 project.
    Conferences, workshops and hearings
  • Expert panel

    Information about the expert panel appointed to consider and decide the Kings Quarry Expansion - stages 2 and 3 application.
    Expert panel
  • Comments from invited parties

    The expert panel invites written comments on the application from the persons or groups set out in section 53(2) of the Fast-track Approvals Act 2024.
    Comments from invited parties
  • Draft decision and conditions

    On 26 November 2025, the Kings Quarry expert panel released its draft decision and conditions.
    Draft decision and conditions
  • The decision

    The expert panel for the Kings Quarry Expansion – Stages 2 and 3 project has granted approvals for the application, subject to conditions.
    The decision