Project summary
The project seeks resource consents for water takes from Lake Pukaki contingent storage. The takes would occur over three consecutive winters from winter 2026 at levels lower than the minimum permitted level of 518mRL, which is a prohibited activity under the Resource Management Act 1991 (RMA). Despite this prohibited activity status, the application does not trigger any ineligibility criteria under section 5 of the Act. The applicant already holds resource consents to operate the lake above the permitted level.
The project also seeks resource consents to install permanent rock armouring on Pukaki Dam at the southern end of the lake. Rock armouring works can only be undertaken when lake levels are lower than permitted, and will take 10-12 weeks to complete from commencement.
The project also seeks a wildlife permit under the Wildlife Act 1953 in case native lizard species require capture and relocation.
Project location
The southern end of Lake Pukaki, approximately 10 kilometres north of Twizel in the Mackenzie Basin.
Project referral
The Minister for Infrastructure referred the project to the Fast-track on 14 August 2025. The application was lodged on 22 April 2025.
Notice of decision Lake Pūkaki Hydro Storage and Dam Resilience Works (002) (PDF, 158KB)
Completeness decision
The substantive application by Meridian Energy Limited was deemed complete on 26 November 2025. The application complies with the requirements of section 46 (2) of the Fast-track Approvals Act 2024. The application was lodged on 5 November 2025.
Memorandum on Completeness and Scope (PDF, 910KB)
Competing applications decision
The substantive application by Meridian Energy Limited was deemed to not have any competing applications or existing resource consents on 9 December 2025. This decision is required under section 47 of the Fast-track Approvals Act 2024.
The application has now been referred to the panel convener for determination by a panel.
Decision of appointment of panel and timing of panel decisions
On 12 February 2026, the panel convener issued a minute regarding:
the appointment of the expert panel
the timeframe for panel decisions for the Lake Pūkaki Hydro Storage and Dam Resilience Works project under clause 2 of section 79 of the Act.
The minute can be viewed on the Correspondence page for the Lake Pūkaki Hydro Storage and Dam Resilience Works project.
-
Referral application
Referral application documents for the Lake Pukaki Hydro Storage and Dam Resilience Works project. -
Substantive application
Substantive application documents for the Lake Pukaki Hydro Storage and Dam Resilience Works project. -
Correspondence
Minutes, directions and other correspondence to and from the panel convener and expert panel regarding the Lake Pukaki Hydro Storage and Dam Resilience Works project. -
Conferences, workshops and hearings
Watch and learn more about conferences, workshops and hearings in relation to the Lake Pukaki Hydro Storage and Dam Resilience Works project.