Approvals granted 2 April 2026
The expert panel for the Southland Wind Farm project granted approvals for the application, subject to conditions.
The expert panel for the Southland Wind Farm project granted approvals for the application, subject to conditions.
Wind farm to include:
construction and operation of up to 55 wind turbines, each up to approximately 7MW in capacity and a ‘tip height’ of up to 220m
electrical reticulation, consisting of underground cables and wind turbine transformers
a wind farm substation to collect the power generated by the wind turbines, located at Jedburgh Station
a switching station (also known as Grid Injection Point (“GIP”)) located adjacent to the existing Transpower 220kV circuit between Invercargill and Dunedin
an overhead single or double circuit 220kV transmission line between the wind farm substation and the GIP to provide connection to the Transpower National Grid
up to two permanent meteorological masts each up to approximately 140m in height
an operations and maintenance building
construction of roading, turbine foundations and 'hard stand' areas adjacent to each turbine.
The project area covers 58km² of privately owned land on Slopedown Hill in eastern Southland, approximately 30km southeast of Gore.
The Minister for Infrastructure referred the project to the Fast-track on 31 July 2025. The application was lodged on 2 April 2025.
Notice of decisions on application for referral of Southland Wind Farm (PDF, 170KB)
The substantive application by Contact Energy Limited was deemed complete on 18 September 2025. The application complies with the requirements of section 46 (2) of the Fast-track Approvals Act 2024. The application was lodged on 29 August 2025.
Decision on completeness and scope – Southland Wind Farm substantive application (PDF, 95KB)
The substantive application by Contact Energy Limited was deemed to not have any competing applications or existing resource consents on 30 September 2025. This decision is required under section 47 of the Fast-track Approvals Act 2024.
The application has been provided to the panel convener.
On 31 October 2025, the panel convener issued a Minute. This covers:
the appointment of the expert panel
the timeframe for panel decisions for the Southland Wind Farm project under clause 2 of section 79 of the Act.
The minute can be viewed on the correspondence page.