Project summary
Earthworks and site work for approximately 1,100 residential allotments.
Project location
Wainui Road, Argent Lane, Lysnar Road, and Cemetery Road, Wainui, Auckland.
Project listing application
Milldale – Stages 4C and 10 to 13 application – Ministry for the Environment website
Completeness decision
The substantive application by Fulton Hogan Land Development Ltd was deemed complete on 24 April 2025. The application complies with the requirements of section 46 (2) of the Fast-track Approvals Act 2024. The application was lodged on 1 April 2025.
Record of decision on completeness and scope − Milldale stages 4C and 10 to 13 (PDF, 71KB)
The Fast-track team will check for any competing applications or existing resource consents before providing the application to the panel convener.
Competing applications decision
The substantive application by Fulton Hogan Land Development Ltd was deemed to not have any competing applications or existing resource consents on 9 May 2025. This decision is required under section 47 of the Fast-track Approvals Act 2024.
Record of decision on competing applications − Milldale substantive application (PDF, 65KB)
The application has now been referred to the panel convener for determination by a panel.
Decision of appointment of panel and timing of panel decisions
On 6 June 2025 the panel convener issued Minute 2 regarding the appointment of the expert consenting panel and the timeframe for panel decisions for the Milldale project under clause 2 of section 79 of the Act.
The Minute can be viewed on the Correspondence page for the Milldale project.
-
-
Expert panel
Information about the expert panel appointed to consider and decide the Milldale project. -
Comments from invited parties
The expert panel invites written comments on the application from the persons or groups set out in section 53(2) of the Fast-track Approvals Act 2024. -
Correspondence
Minutes, directions and other correspondence to and from the panel convener and expert panel regarding the Milldale project. -
Reports and advice
Read reports, advice and further information sought in relation to the Milldale project. -
Conferences, workshops and hearings
Watch and learn more about conferences, workshops and hearings in relation to the Milldale project. -
Draft decision and conditions
On 5 September 2025, the Milldale expert panel released its draft decision and conditions.